Nursery and school fit-out in Dubai: KHDA and Civil Defence rules
A nursery or school fit-out in Dubai is judged by more reviewers than any other commercial project we build. Dubai Municipality checks the build, Dubai Civil Defence checks whether a room full of children who cannot evacuate themselves can be emptied safely, the Knowledge and Human Development Authority checks whether the premises are fit to hold an educational permit at all, and the Dubai Health Authority licenses the clinic. Most operators meet those reviewers in the wrong order. A unit is found, a lease is signed, a designer draws a beautiful early years space, and only then does the application reach KHDA. At that point the ground floor question, the outdoor play area and the evacuation strategy turn into problems no amount of joinery will fix.

The approval that comes before the lease, not after
Both resolutions structure it the same way. An Initial Approval comes first, the educational permit follows once the premises pass inspection.
For a nursery, Article 6 of Resolution 35/2020 requires the applicant to undertake to provide "appropriate premises for conducting the Activity in accordance with the requirements prescribed by the KHDA and the Concerned Government Entities". Article 7 gives that Initial Approval a life of one year, extendable by six months if you ask 30 days before it expires. For a school, Article 6 of Resolution 2/2017 carries the same one year plus six months, and Article 4.5 gives KHDA the job of determining whether a site is suitable and whether the premises meet the requirements.
Read those two clocks together and the programme writes itself. You have twelve months, eighteen at the outside, to take a shell from initial approval to an operating permit. Inside that window sit the lease, the design, the Municipality permit, the Civil Defence cycle, the build, the DHA clinic licence if you need one, and a KHDA inspection of a finished building. A fit-out that would take ten weeks in an office tower is not the constraint. The queue in front of it is.
Article 8.2 of the schools resolution says what the permit application carries: site plans and drawings of the premises, complying with KHDA conditions plus the "technical, engineering, health, environmental, and planning conditions" of the other government entities. That is a coordinated drawing set rather than a concept deck. Dimensioned, labelled, room by room.
So send us the unit before you send the brief. We would rather spend two days measuring a building and telling you it will not pass than eighteen months proving it.
Who reviews what, and what can run in parallel
Several bodies touch an education project, and only some of them can be worked at the same time.
KHDA sits at the front and at the back. Site suitability first, final inspection of the completed premises last. Nothing in the middle of the programme changes that.
Dubai Municipality issues the permit for the physical works, through an approved consultant or contractor. If your building sits under a free zone or a master developer rather than the mainland, the permitting body changes and so does the drawing package. Settle that in week one, using the map in which authority approves your fit-out.
Dubai Civil Defence reviews the fire strategy and issues the clearance without which the building cannot legally operate. It runs alongside the Municipality submission rather than after it, and on education projects it is usually the slower of the two.
DHA licenses the clinic, on its own portal and its own timetable, as a separate application about a separate facility that happens to sit inside your school. DEWA handles load and the supply connection, which matters more than people expect once a commercial kitchen and a full ventilation package land on a villa-sized incomer. Food Control enters only if you cook on site.
The sequencing rule we work to: everything that is a queue goes in early and in parallel, everything that is a build waits for a frozen design. Authority time does not compress when you add labour, and neither does a joinery factory.
Ground floor, outdoor play, and the numbers people quote
A nursery belongs on the ground floor with its own outdoor play area. That is what makes evacuation of non-ambulant children workable, and what every operator in Dubai will tell you the inspection expects.
Here is where honesty matters more than confidence. Nursery consultants in Dubai consistently publish 2.3 square metres of indoor space per child and four square metres or more of outdoor play area per child. Those numbers do not appear in Resolution No. (35) of 2020 itself, which delegates premises requirements to KHDA and the concerned entities rather than listing them. The same applies to the figures quoted for schools, 1.85 square metres per student in primary and 1.95 in secondary, and to the sanitary ratio of one WC per fifteen children and the 1.8 metre play area fence.
Treat those as the planning assumption a designer starts from, and confirm the current KHDA requirement in writing before you commit a lease or a budget to them. A per-child area out by a tenth of a square metre changes your licensed capacity, and with it whether the unit was worth taking.
Abu Dhabi publishes more openly, which makes it a useful comparison. ADEK renamed nurseries Early Education Institutions from the 2024/25 academic year, and its 2024 pre-kindergarten expansion was announced with a standard of 2.16 square metres per child and a cap of 25 per class.
One practical test before you sign. Walk the outdoor area at one in the afternoon in June and look at the shade. Shading structures are a package with a lead time and usually their own approval, and they get discovered in month four by operators who priced them as an umbrella.
What Civil Defence is actually looking at
The Civil Defence cycle moves through drawings approved, installation by an approved contractor to those drawings, site inspection and testing, then the completion certificate. You cannot open without the last one.
On an education project the reviewer reads for one thing above all others. The building holds occupants who will not self-evacuate. Infants have to be carried, three-year-olds led, and that drives escape routing, the width and swing of doors, where a room can sit, and how much protection stands between a child and the way out.
The detail that catches contractors who have only done offices is the interior. Surface spread of flame applies to what you specify on the wall and the ceiling as much as to the structure. Carpets, curtains and the fabric on every soft play element have to carry test certificates, and those certificates belong in the submission package rather than in a promise at inspection. Door closers on rated doors are a submission item too, and they interact badly with early years design, because a self-closer strong enough to satisfy the reviewer is heavy enough to trap small fingers. That is an ironmongery decision taken at drawing stage, with a hold-open on a detector release.
The expensive failure mode here is re-work after a Civil Defence comment. A partition moved to widen an escape route reprices the ceiling, the sprinkler layout, the detection loop, the small power and the joinery on that wall in one stroke, then goes back through the Municipality as a re-submission. Freeze the design at submission and hold it. The Dubai Municipality permit route sets out why that matters on any fit-out; on a project with a fixed August handover it decides whether you open.
The medical room, and what DHA specifies down to the door width
This is the part of an education fit-out with the most published detail and the least published commentary, so it is worth going through properly. DHA's Standards for Clinics in Educational and Academic Settings, document code DHA/HRS/HPSD/ST-22, is currently at version 4.1, effective since 6 November 2025. It applies to DHA licensed clinics in educational and academic institutions, and it is specific about the room. Check you are working from the current version before you brief a designer, since DHA revises these codes without much notice.
Clause 6.1.2 puts the clinic on the ground floor, for accessibility and for evacuation. Clause 6.1.6 requires designated spaces for a waiting area, consultation, treatment, an isolation room and a ventilated medical waste collection room. Clause 6.1.10 sizes the waiting area for at least five patients. Clause 6.1.12 sets doors at 110 centimetres and corridors at 150 centimetres for wheelchair access, wider than a standard commercial leaf, and something to design in rather than discover.
Area is set by enrolment under clause 6.2. Under 1,000 students, 20 square metres. Between 1,000 and 2,000, 30. Between 2,000 and 3,500, 40. Above 3,500 the standard calls for two separate school health clinics at 20 and 40 square metres, and above 5,000 for two at 30 and 40. Plan for the enrolment you are licensed to reach rather than the one you open with, because clause 6.2 explicitly asks for consideration of future expansion.
The isolation room carries its own standard. Clause 7.1.2 sets a minimum of 7.5 square metres. Clause 7.1.3 asks that its design and ventilation be prepared to allow conversion to HEPA filtration, a decision about duct routes and a dedicated extract taken at coordination stage and effectively impossible to retrofit into a finished ceiling. Clause 7.1.7 wants a viewing window from the clinic, or a camera with live feed only, since recording is not permitted. Clause 7.1.9 prefers two doors, one to the clinic and one external, and clause 7.1.6 an accessible toilet attached or nearby.
Finishes are specified too, which answers the question operators usually put to their designer. Clause 6.1.4 calls for flooring that is easy to maintain, readily cleanable, anti-microbial, slip resistant, anti-glare and wear resistant for the location. Clause 6.1.5 calls for walls that are smooth, washable and moisture resistant, with no ledges or crevices that could harbour dust. Name the test method rather than the adjective when you write that specification. Anti-microbial performance in flooring is measured to ISO 22196, and a result against that standard turns a brochure claim into one you can hold a supplier to.
Staffing sits outside the fit-out contract but shapes it. Clause 8.1 requires a DHA licensed registered nurse with a year of experience with children, present at all times students are in the setting under clause 8.2. Clause 8.5 allows an alternative: a registered clinic with full time DHA licensed staff, or a contract with a hospital. Which route you take changes how much room you are building.
Nurseries are a different question. The DHA standard is written for licensed clinics, and many early childhood centres operate with a first aid room and trained staff instead. Ask KHDA and DHA which applies to your model before you draw it, because the two answers produce very different floor plans. Where a licensed facility is involved, the submission logic mirrors clinic fit-out and DHA approval.
Nursery and school: where the buildings genuinely differ
Both fall under educational occupancy, and there the similarity stops.
Evacuation is the first divergence. A nursery is a single-storey problem with adults carrying children. A school is a multi-storey problem with assembly points, phased evacuation and stair capacity, and its fire strategy is a different document with different consequences for the plan.
Sanitary provision differs by more than a ratio. Nursery WCs are scaled down, low level, open or half-height for supervision, with nappy changing and a sluice. A school needs sanitary blocks separated by age and gender, with adult scale fittings in the upper years. The drainage strategy behind those two is not the same, and drainage most often decides whether a building can be converted at all.
Catering separates them again. Nurseries usually run a milk kitchen and a food preparation area under health and safety obligations that Article 13(12) of Resolution 35/2020 extends explicitly to "the safety of the food served to children". Schools frequently run a full commercial kitchen, which brings Dubai Municipality Food Control into the drawing review, along with extraction, make-up air, grease management, fire suppression over the cooking line, floor gullies and a drainage route that either exists already or has to be cut into a slab you may not be allowed to cut. On a converted villa that last point is what most often turns a workable unit into an unworkable one, so settle the catering model before the layout is drawn.
Specialist rooms are a school-only cost band. Laboratories bring gas, fume extraction, emergency isolation and chemical storage. Design and technology rooms bring dust extraction and machine guarding. Art rooms bring wet services and kiln ventilation. Each is a services package rather than a finish, and each one prices far above a classroom per square metre.
Acoustics differ in kind. A nursery is designed for supervision, so sightlines beat separation. A school is designed for concentration, and partition performance, ceiling absorption and door seals become a specification with a number on it.
Then the small physical things that decide whether an early years building works. Socket heights and cover plates. Radius edges on joinery corners within reach. Anti-finger-trap detail on door leaves. Safety glazing at low level as well as at door height. Fixings sized for a wall a two-year-old will hang off. None of that appears on a finishes schedule and all of it is in the price.
What breaks the programme
In the order they usually show up:
A lease signed before KHDA site approval. The most common and the most expensive, because the rent clock starts on a building that may never be permitted, and every obvious fix costs more than the rent.
A design change after the authority submission. Priced during design it is a line item. Priced after approval it is a re-submission plus a repricing of several trades. Priced after the joinery factory has cut sheets, a write-off.
Long lead items ordered late. Shade structures, soft play, laboratory furniture, child-sized sanitaryware and made-to-order joinery all run on factory time, and factory time ignores urgency in a way site labour does not.
The August wall. Schools and nurseries hand over to an academic calendar, so the whole industry wants the same summer and the same inspectors. A programme with no float against a fixed term start will cost you overtime, the most expensive way to buy back a week.
What it costs
We do not publish a rate per square foot for education projects, and any contractor who gives you one on a phone call is quoting a building he has not seen.
The number is decided almost entirely by things outside the finishes. Whether the unit is a shell, a fitted space or a villa being converted. Whether drainage exists where the WCs and the kitchen need to be. Whether the base building carries the cooling and electrical capacity for full occupancy in June, or whether DEWA and a plant upgrade enter the scope. How much of the ventilation package is new, which on a converted residential building is usually all of it. Whether there is a licensed clinic with a HEPA-ready isolation room, and whether there are laboratories. How many weeks the authorities hold the file, since supervision, insurance, hoarding and protection burn at a weekly rate whether or not the drawings change.
Two schools at identical areas finish a long way apart on those grounds alone. The rate per square foot is the output of that arithmetic rather than the input to it.
Questions this raises
Do I need KHDA approval before signing the lease for a nursery or school?
Yes. Article 13(21) of Executive Council Resolution No. (35) of 2020 stops an early childhood centre taking lease of new buildings for the activity without first obtaining the approval of KHDA and the concerned government entities, and Article 13.13 of Executive Council Resolution No. (2) of 2017 applies the same rule to private schools.
How much space does a nursery need per child in Dubai?
Consultants and operators in Dubai consistently quote 2.3 square metres of indoor space per child and four square metres or more of outdoor play area. Those figures are not stated in Resolution No. (35) of 2020, which delegates premises requirements to KHDA rather than listing them, so confirm the current KHDA requirement in writing before you sign a lease. Your licensed capacity depends on the answer.
Does a school in Dubai need a medical room, and how big?
DHA's Standards for Clinics in Educational and Academic Settings, code DHA/HRS/HPSD/ST-22, currently at version 4.1, sets the clinic area by enrolment: 20 square metres below 1,000 students, 30 between 1,000 and 2,000, 40 between 2,000 and 3,500, and two separate clinics above that. An isolation room of at least 7.5 square metres sits alongside it, with ventilation designed to allow conversion to HEPA filtration. A DHA licensed registered nurse has to be present whenever students are in the setting, or a contract with a licensed hospital or clinic covers the service instead.
What does Dubai Civil Defence require for a nursery fit-out?
Drawing approval, installation by a Civil Defence approved contractor to those drawings, site inspection and testing, then the completion certificate that lets you operate. What is specific to a nursery is the assumption that occupants cannot evacuate themselves, which drives escape routing, door swings and widths, and where rooms can sit relative to exits. Carpets, curtains and soft play fabrics need flame spread certification inside the submission package, and self-closers on rated doors need a hold-open and finger protection strategy agreed early.
How is a school fit-out different from a nursery fit-out?
The nursery is single storey, ground floor, with an outdoor play area, scaled-down sanitary provision and nappy changing. The school is multi-storey, with phased evacuation and stair capacity, sanitary blocks separated by age and gender, usually a commercial kitchen with Food Control involvement, and specialist rooms. Laboratories, design and technology rooms and art rooms each carry their own services package.
What is the difference between KHDA and ADEK requirements?
KHDA regulates nurseries and private schools in Dubai under Executive Council Resolutions 35/2020 and 2/2017. ADEK is the equivalent authority in Abu Dhabi, where nurseries were renamed Early Education Institutions and given a new set of policies from the 2024/25 academic year. The standards and the submission routes are separate, so a group operating in both emirates cannot reuse one drawing set or one programme. If you are looking at a unit for a nursery or a school, send the lease drawing and the building name and we will walk it before you commit. Request a fit-out estimate or send the address to +971 56 508 0888. We survey the space, check what the ceiling actually contains, and tell you whether the building will carry the permit you need before the rent starts running.
Send the drawings, or just the address.
We measure, check the services and tell you what the authority will require.
Other notes

FF&E procurement in a Dubai fit-out: who buys the furniture and when
Who buys FF&E on a Dubai fit-out, when to place the order, real furniture lead times from Al Quoz to Italy, Jebel Ali customs rules and who pays for storage.
27 September 2026 · 11 min read
Fitting out an office in DIFC or DMCC: the free zone rules that change the job
DIFC and DMCC approve their own office fit-outs: registered contractors, zone NOCs, FODA, deposits, insurance and the working hours that set your programme.
26 September 2026 · 11 min read
Civil Defence approval for a Dubai fit-out: what it takes
How Dubai Civil Defence approval works for a commercial fit-out: parallel filing, who can submit, certificates, inspection day, and why files get rejected.
25 September 2026 · 12 min read