Restaurant fit-out cost in Dubai: where the budget goes
Published market guides put a restaurant fit-out in Dubai at roughly AED 600 to 900 per square foot for quick service, AED 900 to 1,500 for casual dining and AED 1,500 to 3,000 or more for premium concepts (alrazanaonline, Cost To Open Restaurant Dubai 2026). Kitchen and extraction carry the heaviest share of that. Equipment and loose furniture normally sit outside the rate. Those bands are useful for a first conversation and close to useless for a decision. Here is what the published guides say, side by side:

What a per-square-foot rate actually covers
When a Dubai contractor quotes per square foot, the figure usually covers construction, MEP, joinery and finishes inside the demised area. It does not usually cover kitchen equipment, refrigeration, POS, loose furniture, crockery, signage fabrication or the authority fees. On a restaurant that exclusion list can rival the build itself, because a fryer bank, combi ovens, walk-in cold rooms and a bar backline are capital equipment, not fit-out.
alrazanaonline works a casual dining example of 150 square metres at AED 1.4 to 2.4 million all in. Read that as orientation, not as a quotation. We quote off a drawing, an equipment schedule and a site survey, and until those three exist any number is a guess with a currency sign in front of it. If you want the shape of a budget before you commit to a unit, send the plan and the address through our estimate page.
One thing that moves the rate more than specification does: whether anyone traded food out of the unit before you.
Restaurant kitchen and extraction: the heaviest part of the build
A restaurant kitchen is drawn backwards from the menu. The appliances under the canopy set the extract volume, the extract volume sets the make-up air, and both together set the duct size that has to physically fit through the building you rented. That chain runs in one direction only. Changing the menu after the ducts are ordered means changing the ducts.
What sits inside the kitchen line:
In malls, the riser is the constraint that decides whether the concept is buildable at all. Extraction allocation is finite, it is assigned per unit in the fit-out manual, and a unit with no riser capacity cannot take a hot kitchen regardless of what the leasing agent implied. Ask for the allocated extract and make-up air figures in writing before signing heads of terms.
On street-level units, the fight is the discharge point. The duct has to terminate clear of the surrounding building, and the route from the kitchen to that termination crosses whatever the landlord, the neighbours above and the facade will allow. We settle the route before the kitchen layout is frozen, not after. The mechanics of all of this are covered in detail in our piece on restaurant kitchen extraction, gas and Food Control.
- canopies sized to the appliance line, with filtration appropriate to the cooking type
- extract ductwork in welded or sealed construction, with access panels along the full route for cleaning
- a fan and attenuation package, usually at roof level
- make-up air, ducted and tempered, because an unbalanced kitchen pulls air from the dining room and the dining room gets hot and noisy
- gas, either a cylinder bank in a ventilated external enclosure or a piped supply, with its own approval chain
- hood suppression, interlocked to the gas shut-off
- stainless fabrication, floor gullies, coved skirting and a floor finish that survives hot oil
Front of house: seating, bar and the service spine
The dining room is where the money is visible and where it is easiest to overspend without affecting trade. Seat count, not finish, is what pays the rent. We have redrawn more than one layout to recover four covers that the original design lost to a badly placed waiter station.
The bar is the second wet joinery item after the kitchen counter, and it behaves like a small kitchen: water in, waste out, ice wells, glass wash, multiple power feeds, cold storage, drainage falls under the floor. Bars get drawn as furniture and built as plant. The drainage and the service penetrations have to be set on the slab drawing, which means the bar position is locked earlier than most operators expect.
Then there is the service spine nobody photographs. Waiter stations, POS points, a till drawer that opens without hitting a column, a route from the pass to the furthest table that does not cross the entrance queue, dry store, staff changing, a cleaning materials store that is not the food store, and WCs in the numbers and accessibility standard the code requires. Those spaces are finished, inspectable and fully serviced. On tight units they take floor area away from covers, and finding that out at the layout stage is far cheaper than finding it out at inspection.
Acoustics is the line that gets deleted and then complained about. Hard floor, glass facade, exposed soffit and stone tables make a room that nobody can hold a conversation in, and retrofitting absorption into a trading restaurant means closing it.
The engineering that gets underpriced
Electrical load is the single most common surprise. An all-electric kitchen with induction, combis and cold rooms can need a supply the unit was never designed for, which pushes you into a DEWA load application, a new distribution board, and sometimes switchgear or substation-side work. That is a long item and it does not care about your opening date. Establish the available load and the existing capacity at survey stage.
Drainage is the second. Kitchens need floor gullies, falls, and a grease interceptor before discharge to the public sewer. Dubai Municipality's Local Order No. 8 of 2002 requires that interceptor on restaurants, cafeterias and similar food establishments, and the sizing method reads a minimum capacity off a table that runs from 60 litres to 6,000 litres depending on fixtures, kitchen type, hours and covers served. Put it somewhere a tanker crew can reach without lifting your finished floor.
HVAC is the third. Landlord chilled water comes with a BTU allocation, and a kitchen with full make-up air plus a busy dining room frequently needs more than the allocation assumes. The sprinkler layout also changes the moment you build a new ceiling, and that modification needs its own approval.
Waterproofing under the kitchen and the WCs is the line that looks optional in a value engineering meeting and becomes a tenant dispute two years later when the unit below reports a stain.
Approvals and what they do to the programme
Approvals rarely add much to the cost line. They decide the calendar, which on a leased unit is the same thing as money, because rent runs from handover. We map that calendar against the build programme for every project, which is the part covered on our process page.
The kitchen layout goes to Dubai Municipality food safety for pre-approval before fit-out work starts. Building first and submitting after is the most expensive mistake in this category and we still see it every year, usually because a tenant under rent pressure started demolition the week they got the keys. Civil Defence runs its own chain: drawing approval, installation, inspection, then the fire safety certificate, with gas and hood suppression pulling extra scope in. DEWA sits on the Ejari and the load application.
Depending on where the unit is, the building permit authority differs:
Each one has its own submission format, consultant requirements and inspection habits, so a drawing set prepared for one of them is not a drawing set for another.
We do not publish week counts for these. The figures circulating online come from contractors, not from a published service standard, and the number that actually decides your programme is how many resubmissions you trigger. Complete drawings that show flow, finishes, drainage, gas and ventilation clearly come back faster than incomplete ones by a wide margin. The full chain and the order it runs in is set out in our guide to restaurant fit-out approvals in Dubai.
- Dubai Municipality for most mainland units
- Dubai Development Authority inside its own districts
- Trakhees in the Ports, Customs and Free Zone Corporation areas
Shell and core, or a unit that already traded as F&B
A former restaurant with a live drainage route, a grease interceptor, an extraction riser, a gas provision and a decent electrical supply can save a six-figure sum against a bare shell of the same size. That is the biggest single variable in any Dubai F&B budget, and it is decided when you sign the lease, not when you appoint a contractor.
The catch is condition. An old F&B unit also carries somebody else's ducts, somebody else's suppression system past its certification, a grease trap nobody serviced, and often a reinstatement clause pointing back at the shell. Inherited kit is an asset only if it is sized for your menu and still certifiable. We survey it on that basis and tell operators plainly when stripping out is cheaper than adapting.
On shell and core the opposite risk applies: the honest cost is higher, but you build the services for your menu once, and nothing about the unit argues with the design. Fine dining concepts usually end up here anyway. Our restaurant fit-out page covers how we price the two routes against each other, and Gashisha on Sheikh Zayed Road shows the finished side of one of them.
Where budgets slip
Not on the headline items. Budgets slip on savings that come back as rework.
Joinery ordered before the equipment schedule is frozen is the classic. A machine arrives 40 mm wider than the cutout, or a cold room door swings into a trolley route, and finished joinery comes apart in the final week. Freeze models and service clearances before anything goes for production.
The others we see repeatedly: make-up air cut from the mechanical package to save money, then reinstated after the first trading week in a hot dining room; an extract fan specified on price rather than on static pressure; duct access panels omitted, which makes the system uncleanable and fails inspection; floor gullies set from a drawing that was superseded; shopfront and signage treated as an afterthought when it needs its own approval and its own lead time.
Then there is the landlord. Night work only, lift bookings, hoarding to the manual's specification, approved contractor lists and a refundable fit-out deposit held against conditions you may not have read. None of that appears in a per-square-foot rate, and all of it appears in your programme.
Keep a contingency. Every operator who opened on budget in this city had one, and most of them used it. If you want the cost shape and the approvals path mapped against a specific unit before you commit, send us the plan on +971 56 508 0888. An hour on a drawing is cheaper than a month of rent on a unit that cannot take a duct.
Questions this raises
What is the cost per square foot for a restaurant fit-out in Dubai?
Published guides cluster around AED 600 to 900 per square foot for quick service, AED 900 to 1,500 for casual dining and AED 1,500 to 3,000 or more for premium work (alrazanaonline, 2026). mattermind.ae gives AED 600 to 1,200 for a mid-range restaurant. Those are market ranges rather than quotations, and shell condition shifts them more than specification does.
Why does a restaurant cost so much more than a cafe to fit out?
The hot kitchen. A cafe without gas, fryers or a grill skips the canopy, the make-up air plant, the gas approval and the hood suppression, which is why mattermind.ae puts cafes at AED 400 to 800 per square foot against AED 600 to 1,200 for a restaurant. Add one grill to a coffee concept and you are building a restaurant kitchen whatever the sign says.
Is kitchen equipment included in a fit-out quotation?
Usually not. Per-square-foot rates in Dubai normally cover construction, MEP, joinery and finishes. Cooking equipment, refrigeration, cold rooms, POS and loose furniture are separate capital lines with their own lead times, and on a restaurant they can approach the size of the build. Ask any contractor to state explicitly what sits inside and outside the rate.
How much do approvals add to a restaurant fit-out budget?
Fees are a minor line next to construction. Their real cost is time, because rent runs whether or not you are trading. Dubai Municipality food safety pre-approval, Civil Defence, DEWA and the relevant building authority each have their own submission and inspection, and resubmissions are what stretch programmes. We do not publish week counts, since no authority publishes a binding service standard for them.
How much contingency should a restaurant opening carry?
Enough to absorb one unknown found behind a wall or one authority comment that changes a drawing. We will not put a percentage on it, because the honest figure depends on how much of the unit was surveyed before the lease was signed. An ex-F&B unit with uninspected inherited services needs more contingency than a bare shell with a clean drawing set.
Send the drawings, or just the address.
We measure, check the services and tell you what the authority will require.
Other notes

Prayer room fit-out in Dubai: sizing, wudu areas and approvals
Sizing a prayer room and wudu area for a Dubai office or mall fit-out: area per worshipper, tap counts, drainage, MEP and the approval chain that applies.
19 November 2026 · 13 min read
Laboratory and diagnostic centre fit-out in Dubai: extraction, services and approvals
Laboratory fit out in Dubai: DHA approval before works start, Municipality and Civil Defence permits, FANR for imaging, LEV extraction and backup power.
17 November 2026 · 14 min read
Bar and lounge fit-out in Dubai: the back bar, air and noise
What really decides a Dubai bar or lounge fit-out: back bar layout, ventilation and make-up air, acoustics, and the approvals that set your opening date.
15 November 2026 · 12 min read